Driffield CCTV specialists Frost Completes Major Multi-Phase CCTV Installation with Over 50 Units During the Past 12-18 months
- markarthered
- Jan 24
- 1 min read
Frost Completes Major Multi-Phase CCTV Installation with Over 50 Units During the Past 12-18 months
Over the past 12-18 months, the Frost team have successfully completed a multi-phase CCTV installation project for a client, installing over 50 CCTV units across multiple phases. This was driven by client expansion and additional new buildings to help enhance security across a client’s key operational areas.
Final phase covered installation in:
Cold store
Corridors
Courtyard
Engineering areas
Storage area
Food mixing room
Phase 4 covered installation in:
Canteen
Corridors
Kitchen
Phase 3 covered:
· Installation in raw materials and factory office areas
· Full cabling installation
· Removal of analogue CCTV units, recorders, and legacy wiring systems
Phases 1 and 2 covered installation in:
· Installation in high-risk production and packing areas
Camera locations
The team identified the optimal camera positions to maximise coverage and effectiveness, a key element of this project.
Our client now benefits from a modern, streamlined CCTV infrastructure that supports both operational safety and security across the site.