Driffield CCTV specialists Frost Completes Major Multi-Phase CCTV Installation with Over 50 Units During the Past 12-18 months

  • markarthered
  • Jan 24
  • 1 min read

Frost Completes Major Multi-Phase CCTV Installation with Over 50 Units During the Past 12-18 months

Over the past 12-18 months, the Frost team have successfully completed a multi-phase CCTV installation project for a client, installing over 50 CCTV units across multiple phases. This was driven by client expansion and additional new buildings to help enhance security across a client’s key operational areas.

 

Final phase covered installation in:

  • Cold store

  • Corridors

  • Courtyard

  • Engineering areas

  • Storage area

  • Food mixing room

 

Phase 4 covered installation in:

  • Canteen

  • Corridors

  • Kitchen

 

Phase 3 covered:

·        Installation in raw materials and factory office areas

·        Full cabling installation

·        Removal of analogue CCTV units, recorders, and legacy wiring systems

 

Phases 1 and 2 covered installation in:

·        Installation in high-risk production and packing areas

 

Camera locations

The team identified the optimal camera positions to maximise coverage and effectiveness, a key element of this project.

 

Our client now benefits from a modern, streamlined CCTV infrastructure that supports both operational safety and security across the site.